Kitchen

The plumbers removed some old drain pipes and vents. They began installing pipes by patching up the radiant heat pipes that were broken yesterday.

Dining Room

They poured the new footing and floor. Alex came back around 7 pm to finish the floor.

Pool Area

In preparation for cutting the supports out from under it, they stabilized the entire structure by scabbing on boards to tie the posts together. Then they cut off the bottoms of the posts.