Closing Up

From the floor to the attic, various trades worked to finish up all the rough work in preparation for closing up the walls with sheetrock.

Concrete

Alex filled the two holes in the kitchen floor. No more dirt for Muir to dig in; no more holes to fall in.

HVAC

The guys from Kamor relocated the ducts in the attic and the pipes and conduits that connect the air conditioner with the compressor unit. Since it was added on in the '80s, those pipes were on the outside of the house; now they'll be hidden inside the wall.

Electrical

Ken completed the rough electrical work in the kitchen.

And in the dining room, Ken installed a few receptacles, switches, and a box for an exterior porch light.

 

Framing

Bob and John prepared the upper playroom wall to accept sheetrock, and prepared the window sill to accept a granite top.